Welsh Water invests £13 million to upgrade wastewater network in Builth Wells

Welsh Water invests £13 million to upgrade wastewater network in Builth Wells

Dŵr Cymru Welsh Water is investing £13 million to improve the performance and resilience of the wastewater network in Builth Wells.

Work, which began in October, will see the construction of new drainage infrastructure designed to remove surface water from the wastewater network, creating additional capacity within the local system and helping it operate more effectively during periods of heavy rainfall.

Working with Alun Griffiths Contractors, Welsh Water will also build a new stormwater storage tank to manage increased flows during wet weather. Together, these improvements will help reduce the risk of sewer flooding for local residents while supporting improvements to the quality of the River Wye.

Luke Bentley, Project Manager at Welsh Water, said: "Builth Wells has long been at the heart of agricultural, commercial and community life in Mid Wales, and delivering a project of this scale requires careful planning. Throughout the work, we are balancing the delivery of these important infrastructure improvements with maintaining access to homes, businesses and community facilities.

"These upgrades will not only help increase the resilience of the local wastewater network but reduce the risk of internal flooding and support improvements to the local environment for years to come."

The project is part of Welsh Water's wider investment programme, which will see more than £4 billion invested between 2025 and 2030 to improve services for customers and protect the environment. Of this, £2.5 billion will be invested in environmental improvements, including projects such as the one in Builth Wells.

The phased series of works includes:

Area 1. Early December 2026 to 12/1/27: Roundabout shut at Park Rd / Broadway, work going into Broadway etc. Garth Rd will be two way traffic, with no parking on road in Garth Rd. There will be a HGV diversion away from Town so no HGVs going through it.

Area 2. 13/1/27 to 30/4/27: Garth Rd up to the roundabout. Lane closure with traffic light control…rolling closure.

Area 3. Early December 2026 to 19/1/27: This work will be concentrated on the Groe itself, around the area of the footpath going from around the memorial garden area to near the Bronwye Guest House. Dwr Cymru will access this via the Groe Carpark.

Area 4. 20/1/27 to 2/6/27: Work will go from the Groe, up North Rd to the junction with Park Rd & Church St, then up Church Street going past the carpark entry to the Greyhound towards the junction with West street/ Garth Rd, then across the junction up into Hospital Rd for a short distance. There will also be 2 nights of overnight work ON each the two junctions mentioned above. All the above will be rolling roadworks.

Area 5. 3/6/27 to 29/7/27: Hospital Rd going past the Primary School

Area 6. Park Rd: All but eliminated as a necessity owing to pushing work back westwards and being undertaken in area #1.

Area 7. 4/5/27 to 5/7/27: From Broadway going up the footpath alongside Ysgol Calon Cymru, then past the Bowling club up to the river.

Area 8. 4/6/27 to 15/9/27: Broadway up to the Park Rd roundabout. Potential roundabout closure with Garth Rd being two way again.

Area 9. 16/7/27 to 30/9/27: Smithfield Rd into Western Grove

Area10. January 2028 to December 2028: This is to fit the huge Storm Tank. They are not sure whether this will either go under the Groe Carpark or the area where the Stone Circle is presently situated. All work should be able to be carried out on the Groe, but may mean a large part of it being taken over by Dwr Cymru vehicles and equipment

Comment Guidelines

Iconic Media encourages reader discussion on our stories. User feedback, insights and back-and-forth exchanges add a rich layer of context to reporting. Please review our Community Guidelines before commenting.

Local news you can trust
Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice