Council-backed firm wants permit to burn up to 6,000 tonnes of green waste per year at Ludlow incinerator
A company backed by Shropshire Council has applied for a permit to run a new £2m green waste recycling facility in Ludlow - which could burn up to 6,000 tonnes of waste per year.


Biodynamic Carbon Ltd, a joint venture between Shropshire Council and Powys-based Woodtek Engineering Ltd, has applied to run a "small waste incineration plant" at a proposed processing centre for green waste in Ludlow.
A public consultation on the scheme was opened this week, and runs until June 16.
In March this year, the company was granted planning permission to use a council-owned former biodigester site on Coder Road as a home for a new "pyrolysis" plant, which it says will help the county hit climate change targets, produce renewable energy and generate profits from the sale of a waste product known as biochar.
The firm already operates a similar facility near Welshpool in Powys.


Shropshire Council says that, once up and running, the plant is expected to produce between 1,000 and 2,000 tonnes of biochar per year using "low-grade" green waste from council sites.
"The process is proposed to have a single pyrolysis reactor capable of processing approx 6,000 tonnes of waste/wood per year and produce around 1.4 MW of power as heat most of which is used onsite as primary heat," said a statement submitted with the application.
"The reactor is estimated to generate up to 2,000 tonnes per year of biochar."
Supporting information supplied by Biodynamic Carbon said there were "significant environmental and economic benefits" to the scheme, including reducing the need to process waste materials, but also from the sale of electricity back to the national grid.
However a noise assessment supplied with the scheme identified "adverse impact" to some nearby residents from noise levels, with properties subject to "occasion(al) buzzing from the chipper, vehicle movements (reversing alarms), and soft clashes/thumps", which the report asserted would be "present but not intrusive".
The report said the main source of noise in the area was from the nearby A49 road, and that the new pyrolysis plant was therefore "unlikely to significantly impact affect existing noise levels". Noise modelling carried out as part of the application identified that one property could be subjected to noise levels above 50 decibels in what it described as a "worst case scenario".
"The sounds generated are almost identical to road traffic, HGV movements, and loading shovel operation some of which already occur on the industrial estate. It is very unlikely that the activities will be clearly distinguishable from existing ambient noise in the area," the report added.
Around 700 vehicle movements per year are expected to take place as part of the plant's operations.
A separate report added that the risk of odour issues generated by the plant was identified as "low" - but said complaints would be investigated immediately.
"Where an event occurs, and compromised combustion creates offensive odour the potential for odour impact is moderate. It is unlikely that industrial receptors will be significantly adversely affected. The duration of such events is likely to be short, and the controls in place should reduce frequency to a negligible level."
The consultation is available to view on Shropshire Council's online portal.