Volunteer effort keeps Shropshire canals in good order this June
Shropshire Union Canal Society: June 2026 work party report
June's work party ran for five days, with record volunteer numbers and several activities. It was the second successive work party with two days of preparation before the main work party started on Friday. Restoration project manager Tom Fulda said two full days of profiling the channel were again required to stay ahead of progress by the lining and blocking team, supported by high volunteer numbers.




On Thursday, work began to add riprap and soil over the liners. This continued through the rest of the work party and involved transporting materials over a long distance. On the offside bank, buckets of riprap were barrowed over the laid blocks. On the towpath bank, materials can be delivered by power barrow along the towpath. By Sunday afternoon, 150 metres of towpath bank had been completed and reseeded. With deliveries completed, it was then possible to apply the wear course (very fine chippings/quarry dust) to the towpath surface.


The main work party started on Friday, joined by corporate volunteers including returning volunteers from Arcadis and new volunteers from Aico. A new attendance record of 42 people was set that day, supported by refreshments provided by Kath, Margaret and Steve.


From Friday to Sunday, lining and blocking continued, with a further 45 metres completed. Excavation of material through Schoolhouse Bridge also progressed, despite a brief excavator breakdown on Friday. Material removed is currently being taken to the spoil heap in the compound. While nothing is confirmed, potential "homes" for this material have been identified that would avoid waste disposal costs.


With substantial material removed, work started to set out the position of the wash wall to be constructed through the bridge.
With warmer weather after a mild but damp winter and early spring, strimming and weed bashing were carried out at the Schoolhouse and Crickheath compounds and around newly planted and laid hedging.


As Phase 2 (north of Schoolhouse Bridge) approaches completion, focus is turning to Phase 3 (Bridge 86 Schoolhouse Bridge to Bridge 85 Malthouse Bridge). Clearance is due to resume, and work began on Friday.
On Sunday, the raffle for the members 60th Anniversary Monty Cruise was drawn.
Shropshire Council and Canal & River Trust (CRT) visited on Friday afternoon. Visitors were Matt Potts and Hannah Smith (Shropshire Council) and James Dennison and Kate Hanks (CRT).