The owner of a takeaway in Telford has launched an appeal after being ordered to take down a timber extension that was reportedly built without planning permission. 

The owners of Kebab King on Madeley's High Street are appealing an enforcement notice issued by Telford & Wrekin Council over the unauthorised erection of a timber extension to the side and rear of the takeaway.

The enforcement notice, issued in April, ordered the business to permanently remove the extension from the land within four months.

Documentation doesn not reveal when the extension was built, but imagery from Google Maps suggests it went up sometime between March 2021 and June 2022.

In the notice, the council said the "overall design, form and materials" of the structure "fails to be in keeping with the character and appearance" of the area, which is within the Severn Gorge Conservation Area the Ironbridge Gorge World Heritage Site.

It continued: "In terms of the scale of the unauthorised side and rear extension, particularly the footprint, this is considered to be neither a modest, nor subservient addition on the application site and fails to be proportionate to the host building.

"The impact of the unauthorised extension is further exacerbated by the positioning of the works and their prominence within the surrounding area; resulting in an incongruous and unsympathetic addition within the surrounding streetscene.

"Furthermore, the works have resulted in harm to the setting of neighbouring heritage assets, particularly Grade II listed No. 59 High Street, and the Buildings of Local Interest known as Nos. 35-40 High Street and the Madeley Community Centre (formerly a Methodist church)."

The enforcement notice - which was issued in April - ordered the business to permanently remove the extension from the land within four monthsplaceholder image
The enforcement notice - which was issued in April - ordered the business to permanently remove the extension from the land within four months

The council said that planning permission should not be granted for the building, "because planning conditions could not overcome the problems identified".

Now, Shevki Aribas, who is listed on Companies House as manager of Madeley Kebab and Pizza Ltd, has appealed the enforcement notice with the Government Planning Inspectorate.

Statements from both the applicant and the council will have to be submitted to the inspector by June 12, with final comments due by July 3.

The case will then be considered by the inspector who will determine if the extension will have to be removed.

Related topics:

Comment Guidelines

Iconic Media encourages reader discussion on our stories. User feedback, insights and back-and-forth exchanges add a rich layer of context to reporting. Please review our Community Guidelines before commenting.

Local news you can trust
Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice