Papers reveal extent of huge North West Relief Road funding gap
Shropshire Council's financial strategy has revealed the extent of the funding still required for Shrewsbury's controversial North West Relief Road.
The strategy, which is due to be considered by the authority's cabinet next week, sets out the detailed costs of projects being considered by the council.
The issue of funding for the North West Relief Road has been unclear for some time.
Costs on the project are known to have increased significantly from the original £81m estimate - but the council has remained tight-lipped over the exact amount it needs to build the road, if it finally gets planning permission.
But now, under the priority capital schemes section of the proposed financial strategy, the council lists a 'budget uplift' as being required for a funding gap with the scheme.
It puts the amount required at £111.4m, and lists the source of the funding as 'external grants'.
Responding to queries about where the grant will come from, the council said it would explain the options in its 'Full Business Case' (FBC), which is yet to be published.
It has been anticipated that the FBC would go before full council later this month, but the authority was unable to confirm a date for the document to be considered.
A spokesman for the council said: "The Full Business Case (FBC) for the Shrewsbury North West Relief Road will spell out clearly the full costs of the scheme, including all associated professional fees, carbon management costs and environmental mitigations and compensation, added to the market tested build costs following the recent procurement exercise.
"It will also fully explain any options for required local match funding sources to be used by the council over and above external grant allocations though the Department for Transport (DfT) and the former Marches LEP."
Earlier this week the officer overseeing the scheme told the council’s Audit Committee that he was unable to say when the FBC would be published.
“There are a number of things linked to that – discharging planning conditions etc,” said Andy Wilde, assistant director for infrastructure.
“I’m working with the team at the moment to understand what that timeline looks like. So I will need to update on that because I don’t have a clear position at this moment in time.”
If the FBC does not go before members at full council, it means it will not be considered before the elections in May of this year.
Councillor Roger Evans, the joint leader of the council's Liberal Democrat group, said the committee was previously told the FBC would available in September - then December, before February was suggested.
“We seem to be drifting while this council continues to spend money that it can ill-afford to lose,” said Councillor Evans.
“This is a multi-million pound project, it has been stressed that it’s at risk. The business case is still going to go to government, and they will come forward as to whether they’re going to fund it or not.
“But Shropshire Council is still spending millions on this case with no planning permission yet issued.”