New North West Relief Road carbon offsetting plan set for decision after original proposal deemed 'impossible'

Councillors will be asked to sign off new measures to tackle the carbon impact of Shrewsbury's North West Relief Road - with previous proposals deemed 'impossible'.

Shropshire Council's Northern Planning Committee will be asked to approve changes to the authority's commitment to deal with the amount of carbon which will be created in the construction of the controversial road.

It comes after fresh methods for estimating the impact of the plans have seen the expected carbon cost more than double - from 26,711 to 55,904 tonnes of carbon.

The changes mean the council is now saying that the project will take another 20 years to become 'carbon neutral'.

Originally the council had planned to meet the target by 2030, but it is now proposing to extend the deadline to 2050.

A report prepared for the committee by planning officer Mike Davies said: "In terms of mitigating and offsetting the now larger carbon impact, the applicant has reiterated their commitment to owning the carbon from the North West Relief Road (NWRR).

"However, offsetting the scheme’s impact by 2030 is now considered impossible. Accordingly, the applicant has proposed that planning condition 41 be revised to allow the applicant until 2050 to achieve carbon neutrality of the scheme’s impact."

The report, which will be considered by the committee on Tuesday (January 21), also outlined how there could be a relaxation in where the council can get 'carbon credits' from to offset the scheme.

Carbon credits are units that can be purchased by organisations in an arrangement where another organisation carries out a project to remove carbon, such as planting trees.

The planning report explained the council will now be able to 'source' carbon credits from outside the UK.

It stated: "This increased flexibility in the wording would also allow the applicant to source carbon credits from further afield which potentially will result in expenditure not only outside of the county, but outside of the UK on potentially less reliable carbon offsets.

"Therefore, it is critical that a hierarchy of local, regional, country and international offsets is put in place and every effort made by the applicant to prioritise delivery of offsets on this basis, as opposed to sourcing cheaper offsets abroad which are less reliable and more difficult to monitor."

Mr Davies' report added: "The increase in carbon and delays to the project programme mean that the scheme’s estimated residual carbon impact cannot be offset by 2030 in line with the council's commitment as an authority to be carbon neutral by 2030.

"The applicant proposes to have by 2030 identified and committed to sufficient measures needed to offset the scheme’s carbon impact.

"It is acknowledged that the full residual impact will not have been offset by 2030, but the process adopted will ensure the scheme’s impact is offset by 2050 at the latest.

"It is therefore important to flag up that this raises a conflict between the council’s stated objective of being carbon neutral by 2030 and the applicant's goal of offsetting the impact of the scheme by 2050. It is considered that this is a material consideration that needs to be considered."

Related topics:

Comment Guidelines

Iconic Media encourages reader discussion on our stories. User feedback, insights and back-and-forth exchanges add a rich layer of context to reporting. Please review our Community Guidelines before commenting.

Local news you can trust
Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice