New designs for Telford Theatre revealed - along with cause of delays
It was originally hoped the new theatre would open this winter
The cause of delays to the Telford Theatre project has been revealed with the submission of new designs.
Updated designs for the redevelopment of Telford Theatre have revealed that more demolition work than was originally planned is needed, as prior work uncovered structural issues.
It’s now been more than two years since Telford Theatre in Oakengates closed as redevelopment work on the town centre began.
Previously, it was envisioned that the new and improved theatre would reopen this winter, but the construction site has fallen quiet since the demolition works earlier this year.




Telford & Wrekin Council have remained tight-lipped about the cause of the delay but claimed the new designs would make the theatre “even better”.
Now, the plans have been made available to the public, with documents revealing that a part of the building which fronts Limes Walk is “not structurally sound” and now needs to be demolished.
Documents state: “Through ongoing design evolution and building condition surveys it has become apparent that the two-storey block fronting Limes Walk, shown to be retained within the original planning permission, is not structurally sound and is no longer feasible to refurbish as part of the wider development.
“It is thus proposed to demolish the block and substitute for a comparably scaled massing of development in its place.”




Other changes include the relocation of a substation from Limes Walk to the main car park, and some material changes - including a new “glazed curtain wall” front Theatre Square and the introduction of red metal cladding.
Documents state many of the design amendments are required “in order to ensure viability, buildability and achieve where possible design enhancement”.




Earlier this month, Telford & Wrekin Council leader Councillor Lee Carter said: “We know that Telford Theatre is an eagerly anticipated project throughout the Oakengates and wider community and it’s one of our biggest investment projects across the borough and full demolition will make way for a new theatre design which is even more exciting than the previous plans.
“We are committed to bringing plans for this exciting new facility to fruition and seeing the construction of the new building start to take shape as soon as possible once these plans for an upgraded design are approved.
“The theatre will attract visitors from far-and-wide and drive more footfall to Oakengates town centre.”
The full application is available to view online on Telford & Wrekin Council’s planning portal using reference number: TWC/2026/0608