Natural Resources Wales (NRW) has successfully completed repairs to the Glasbury flood defence wall. following a programme of essential maintenance work.

A programme of essential maintenance work followed the removal of a willow tree earlier this year after engineers confirmed it had weakened the structure and increased flood risk to nearby homes.

The completed repairs have restored the integrity of the flood defenceplaceholder image
The completed repairs have restored the integrity of the flood defence | Natural Resources Wales

The completed repairs have restored the integrity of the flood defence and will help ensure it continues to reduce flood risk to properties in the village for years to come.

The completed repairs  of the flood defence help ensure it continues to reduce flood risk to properties in the village for years to come.placeholder image
The completed repairs of the flood defence help ensure it continues to reduce flood risk to properties in the village for years to come. | Natural Resources Wales

Ryan Griffiths, Senior Engineer at NRW, said; "We're pleased to have completed these repairs successfully.

“Completing maintenance projects like this during the summer helps ensure our flood defences are in the best possible condition ahead of autumn and winter, when storms and flooding can place greater pressure on these assets.

"I'd like to thank local residents and road users for their patience and understanding while the work was carried out.”

Imported clay was then compacted around the wall and foundations to create an impermeable layer, helping to prevent water passing through the structure, improving its long-term resilienceplaceholder image
Imported clay was then compacted around the wall and foundations to create an impermeable layer, helping to prevent water passing through the structure, improving its long-term resilience | Natural Resources Wales

The flood wall and its foundations were exposed to allow repair works to take place. Imported clay was then compacted around the wall and foundations to create an impermeable layer, helping to prevent water passing through the structure, improving its long-term resilience.

Topsoil has been reinstated, the area re-seeded with grass cover, and the access road to the site has also been improved and resurfaced.

The repairs form part of NRW's ongoing programme of work to maintain and improve flood risk management assets across Wales, helping to minimise the impact of flooding on communities and improve resilience ahead of periods of severe weather.

Comment Guidelines

Iconic Media encourages reader discussion on our stories. User feedback, insights and back-and-forth exchanges add a rich layer of context to reporting. Please review our Community Guidelines before commenting.

Local news you can trust
Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice