Two-week closure planned for busy Shrewsbury road as stalled gas works resume

Porthill Road will be closed from Monday, August 10 to August 24

A busy road in Shrewsbury is set to close for two weeks next month as stalled work to replace a gas main gets back underway.

Porthill Road will be closed from Monday, August 10 to August 24 to enable Cadent Gas to complete gas main replacement work that was temporarily suspended earlier this year.

During the earlier work, as operatives progressed towards the Pengwern Road junction it was identified that the gas main deviated into the centre of the road.

Porthill Road in Shrewsburyplaceholder image
Porthill Road in Shrewsbury | Google

As a result, Cadent had to temporarily suspend work on the section of Porthill Road between the Shrewsbury School entrance and the Pengwern Road junction.

It has now been established that Cadent will require a full road closure on Porthill Road to complete the outstanding work.

Shropshire Council said the work will be carried out during the school holiday period to minimise disruption and reduce the impact on nearby schools.

Whilst the gas main work is being carried out, Severn Trent will also rectify a blockage within its sewer network - reducing the need for further disruption on Porthill Road at a later date.

A signed diversion route will be in place while the road is closed, and access to affected properties will be maintained.

The proposed surface dressing scheme for Porthill Road has been deferred to allow Cadent and Severn Trent Water to complete their work. The surface dressing scheme will be programmed separately at a future date.

Comment Guidelines

Iconic Media encourages reader discussion on our stories. User feedback, insights and back-and-forth exchanges add a rich layer of context to reporting. Please review our Community Guidelines before commenting.

Local news you can trust
Follow us
© 2026 Iconic Media Group Ltd. All rights reserved.Cookie SettingsTerms and ConditionsPrivacy notice