A49 roadworks overrun as temporary lights cause long delays and cancelled bus services
National Highways said “unforeseen circumstances” have caused the scheme to overrun
Roadworks on the A49 are expected to continue for longer than expected after National Highways reported “unforeseen circumstances”.
Temporary traffic lights on the A49 in Craven Arms are set to remain in place longer than originally planned after National Highways confirmed delays to ongoing maintenance work.
The three‑way lights installed on Monday (June 15) have been causing significant queues and long tailbacks along the busy south Shropshire route.
A spokesperson for National Highways said: “Due to unforeseen circumstances, our maintenance work on the A49 is taking longer than expected.
“We appreciate the congestion this is causing for road users, and we’re sorry for the disruption to journeys.
“Safety remains our priority, so temporary traffic management will need to stay in place until the work is completed.
“Our teams are working hard to carry out the remaining activities and we’ll reopen the road as soon as possible.”
The delays have created particular difficulties for Minsterley Motors, which operates the 435 service between Shrewsbury and Ludlow.
Earlier this week, the company reported being forced to cancel two services after severe congestion at the lights caused knock‑on delays.
On Tuesday a spokesperson said buses were experiencing “severe congestion” at the traffic lights; one was reportedly stuck in the queue for more than 20 minutes.
Two bus journeys were subsequently cancelled in order for the company to remain legally compliant with limits on drivers’ working hours.
Minsterley Motors has warned passengers that further disruption remains possible while the roadworks continue.
Comment Guidelines