MPs accuse Government of dealing consumers a ‘bad hand’ over Hinkley power station

MPs warn that consumers are being “locked into” an expensive deal lasting 35 years ovedr the new nuclear power station at Hinkley.

Published
Last updated
Artist impression of new Hinkley Point C nuclear power station (EDF Energy/PA)

Consumers have been dealt a “bad hand” by the Government over the near £20 billion Hinkley Point C nuclear power station, facing costs running to many times the original estimate, it has been warned.

A committee of MPs voiced concerns that consumers are “locked into” an expensive deal lasting 35 years, questioning why the Government did not revisit the terms between the original go ahead in 2013 and now.

The Public Accounts Committee said no-one was protecting the interests of energy consumers over the deal to agree a so-called strike price of £92.50 per megawatt hour of electricity generated by the power station, which will be operated by French energy giant EDF.

Hinkley Point nuclear power station
Hinkley Point C power station under fresh scrutiny from MPs (EDF Energy/PA)

The value for money case for supporting Hinkley weakened after the Government agreed provisional terms in 2013, with the Business Department forecasting that consumers will now pay £30 billion in top-up payments over the contract’s 35 years, five times more than the £6 billion expected four years ago, said the report.

Labour MP Meg Hillier, who chairs the committee, said: “Bill-payers have been dealt a bad hand by the Government in its approach to this project.

“Its blinkered determination to agree the Hinkley deal, regardless of changing circumstances, means that for years to come energy consumers will face costs running to many times the original estimate.
“The Government made some grave strategic errors here and must now explain what it will do to ensure these are not repeated.

“But more than that, it must deliver the supposed wider benefits of this project – benefits Government has talked up progressively as the case for Hinkley Point C has weakened, but which it has no plan to secure.

“Government credibility in this area will inevitably be questioned when – by its own admission – it doesn’t know what UK workers and business will gain from this project, and appears to have no coherent idea of what to do about it.”

EDF Energy said in a statement: “The cost of Hinkley Point C for customers has not changed and they will pay nothing for its reliable, low carbon electricity until the station is completed.

“EDF and its co-investor CGN take the risk of increased costs during construction.

“The agreed price is lower than 80% of other low carbon capacity contracted so far and the project has restarted UK nuclear construction after a quarter century.

“Construction is fully under way and is already delivering a huge benefit to British jobs, skills and industrial strategy.

“Hinkley Point C makes it possible for future nuclear new build projects to be significantly cheaper for customers.

“We look forward to working with HM Government to take advantage of this possibility for our projects at Sizewell and Bradwell and to make sure the UK captures the full consumer and industrial benefit of Hinkley Point C.”

Prospect deputy general secretary Sue Ferns said: “Nuclear creates both clean power and thousands of jobs, from apprenticeships to highly-skilled jobs, and its economic impact should not be underestimated despite the challenges Hinkley Point faces in its delivery.

“The government needs to take control of any uncertainty around recruitment and either work towards remaining in Euratom or negotiate a deal which would allow free movement of the nuclear labour force to continue unhindered”.